City of Clayton, MO
Home MenuCentral Business District Resurfacing
Summary
The City of Clayton has received federal grant funding for the Central Business District (CBD) Resurfacing Project to mill and overlay the streets in the downtown area. This project will also address non-compliant ADA curb ramps and brick paver crosswalks to replace stamped asphalt crosswalks. The project consists of two phases with construction currently underway on Phase 1.
Phase 1
The City has awarded the contract for Phase 1 (which includes Bonhomme and Meramec Avenues) to Byrne & Jones Construction. Crews have substantially completed the project and over the next few weeks will be working on the remaining punch list items.
Construction work is weather dependent, so the schedule is subject to change. Any changes to the project schedule will be posted here, so please continue to check this site for the latest updates and specific street closures for each weekend.
This website will be the primary source for up to date information throughout the design and construction of the project. As updates are available (particularly during construction), they will be posted on this page. The short URL for future access is www.claytonmo.gov/cbdresurfacing.
Task | Start Date* | Duration |
Mobilization/Saw-cutting/Traffic Control | COMPLETE | COMPLETE |
Sidewalk and Curb Ramp Improvements | COMPLETE | COMPLETE |
Milling/Paving - Phase A (Bonhomme Avenue) | COMPLETE | COMPLETE |
Milling/Paving - Phase B (Meramec Avenue) | COMPLETE | COMPLETE |
Concrete Crosswalks | COMPLETE | COMPLETE |
Final Signage/Striping |
COMPLETE |
COMPLETE |
*start dates and duration are estimates and subject to weather/work delays
Overall Project Area - Phase 1
Contact
Rich Wilburn, PE
(314) 290-8565
rwilburn@claytonmo.gov